Construction AP automation: what to check before you pay a subcontractor

For AP and project accounting teams at general contractors. See what to check on each subcontractor's pay application before a payment goes out, and which of those checks software can run.

A pay application summary sheet with a column of boxed totals beside a continuation sheet of ruled rows, with a certificate sheet, a waiver slip and a hard hat in front and a dotted path from one total to a green check

Key takeaways

  • Construction AP automation reads the invoices, pay applications and paperwork that suppliers and subcontractors send a general contractor. It checks each document before any money goes out.
  • Start with the math on the pay application. On AIA's G702, current payment due is line 6 minus line 7. That's the total earned less retainage, minus what earlier certificates for payment already covered.
  • After the first month, a subcontractor usually sends two lien waivers. A conditional waiver covers this month's payment. An unconditional waiver confirms that the subcontractor received last month's payment. California and Texas set the wording of each type in law.
  • A certificate of insurance confers no rights on its holder. It's for information only, so on its own it doesn't make you an additional insured. Check its limits and dates against the subcontract, and ask for the additional insured endorsement too.
  • Docsumo reads invoices. It can also read pay applications and lien waivers, because it can read any document a large language model (LLM) can read. Checking a certificate against contract requirements compares two documents, so it's a cross-document check, on the Enterprise plan.
On this page
  1. Why construction AP is harder than paying invoices
  2. What comes in with a subcontractor's pay application
  3. How to check the pay application itself
  4. Lien waivers come in four types, and the law can set the wording
  5. The subcontractor's certificate of insurance and W-9
  6. How automation fits the way you pay subcontractors
  7. Try it on last month's pay applications
  8. Frequently asked questions

Construction AP automation reads the bills a general contractor has to pay. Those are invoices from suppliers and pay applications from subcontractors. The pay applications come with lien waivers, and a new subcontractor also sends proof of insurance. The software checks each one against the subcontract or the PO before money goes out. Documents that pass move on to approval. The rest go to your accounts payable (AP) team, with the reason.

Why construction AP is harder than paying invoices#

Most AP teams pay for goods that were ordered and delivered. A general contractor's AP team also pays for work in progress. A subcontractor doesn't bill per delivery. It bills each month for the share of its work that's done, measured against a schedule of values. That schedule lists the work items in the subcontract, each with its dollar value.

The payment isn't the full amount billed, either. The general contractor holds back part of each payment as retainage, at the rate the subcontract sets, and pays it later. So each pay application has to carry what was billed before, what was held back and what's left to finish. A mistake in one month carries into the next.

Then there's the paperwork that has to be in place before money moves. A subcontractor that isn't paid can claim a lien on the project, or claim against a payment bond. So general contractors often ask for a lien waiver with each payment. They also want a current certificate of insurance and a W-9 on file. Payment deadlines can be short, too. On federal jobs, the Prompt Payment Act requires a clause in each subcontract. Under it, the prime contractor pays the subcontractor for satisfactory work within 7 days of being paid by the agency.

What comes in with a subcontractor's pay application#

A pay application rarely arrives alone. Most months the subcontractor sends a package. It holds the application, its continuation sheet, the lien waivers and any change orders. A new subcontractor also sends a certificate of insurance and a W-9.

DocumentWhat AP readsChecked against
Pay application (AIA G702 or G702S, or your own form)Contract sum, change orders, work completed and stored, retainage, earlier payments, current payment dueThe subcontract, your change order log and last month's application
Continuation sheet (AIA G703 or G703S)Each schedule of values line, with its scheduled value, work this period, stored materials and percent completeThe approved schedule of values and the project manager's review of the work
Conditional lien waiverClaimant (the subcontractor), customer (you, the general contractor), job, amount, and the through date on a California formThis month's current payment due
Unconditional lien waiverClaimant, job, amount received, and the through date on a California formWhat you paid last month
Change ordersNumber, amount, signaturesYour change order log
Certificate of insurance (ACORD 25)Insurers, policy numbers and dates, limits, additional insured and waiver of subrogation boxes, certificate holderThe insurance terms in the subcontract
W-9Legal name, tax classification, taxpayer identification number (TIN), signatureThe subcontract and your vendor record
Supplier invoiceVendor, PO number, job and cost code, line items, totalsThe PO and the delivery ticket

AIA's subcontractor version of the pay application is the G702S. It goes with the G703S continuation sheet and covers work completed, materials stored, retainage, previous payments and change orders. The subcontractor signs it, has it notarized and sends it to the general contractor. AIA's instructions say to pay the subcontractor named on the form, and no other party unless the form says so.

Some general contractors use their own pay application forms instead. AIA doesn't publish a standard schedule of values form, so each subcontractor's continuation sheet can look different.

Supplier invoices go through ordinary construction invoice processing. Each one is matched to its PO and the delivery ticket. The invoice processing page shows how Docsumo handles them.

How to check the pay application itself#

Start with the summary page. AIA's G702 has nine numbered lines. The first two come from the subcontract and its change orders. You work out the rest from those lines, the continuation sheet and last month's certificate for payment. Here they are for a subcontractor's fourth application on a $480,000 subcontract, with retainage at 10%.

LineWhat it showsAmountWhere it comes from
1Original contract sum$480,000The signed subcontract
2Net change by change orders$24,000Change orders you approved
3Contract sum to date$504,000Line 1 plus line 2
4Total completed and stored to date$302,400Column G total on the continuation sheet
5Retainage$30,24010% of completed work ($286,400) plus 10% of stored materials ($16,000)
6Total earned less retainage$272,160Line 4 minus line 5
7Less previous certificates for payment$209,520Line 6 of the third application
8Current payment due$62,640Line 6 minus line 7
9Balance to finish, including retainage$231,840Line 3 minus line 6

The third application showed $232,800 completed and stored. So this month adds $69,600 of work and materials. After 10% retainage, that leaves the $62,640 on line 8. If any line doesn't add up from the others, send the application back to the subcontractor or to the project manager.

  • Contract sumLine 1 matches the signed subcontract. Line 2 matches the change orders you approved, and an unsigned change order doesn't count.
  • Schedule of valuesEach scheduled value on the continuation sheet matches the approved schedule. Look for new lines and for value moved from one line to another.
  • Work this periodThe percent complete on each line matches what the project manager saw on site. No line goes over 100%.
  • Column mathOn each line, columns D, E and F add up to column G, and C minus G gives H. The column G total carries to line 4.
  • RetainageIt's held at the subcontract's rates. The form has one rate for completed work and one for stored materials.
  • Earlier paymentsLine 7 matches line 6 of the last application, as you certified it. If you changed an amount last month, the new application should carry your figure.
  • Payment dueLine 8 is line 6 minus line 7. The conditional lien waiver shows the same amount.

Lien waivers come in four types, and the law can set the wording#

A lien waiver is a signed release. In it, the subcontractor gives up its lien and payment bond rights for work up to a given date, in return for a payment. There are four types. They differ by whether the payment has arrived and whether it's the final payment on the job.

  • Conditional, progress

    Comes with each monthly pay application, before you pay. Match its amount to this month's current payment due. On a California form, match its through date to the end of the billing period. A Texas form has no through date. It covers the work in the pay request attached to it.
  • Unconditional, progress

    Comes after a payment has cleared. Match its amount to what you actually paid last month.
  • Conditional, final

    Comes with the final pay application. It covers the balance still owed, retainage included.
  • Unconditional, final

    Comes after the final payment, retainage included. Keep it with the closeout records.

Some states set the exact wording. California's Civil Code has a form for each type, in sections 8132 to 8138. A waiver releases the owner, the construction lender or the payment bond surety only if two things are true. It must be in substantially the form in the law, which means close to its wording. And the claimant, the subcontractor giving up its rights, must sign it. A conditional waiver also needs evidence of payment, such as the subcontractor's endorsement on a check that has cleared. An endorsement is the payee's signature on the back of the check.

Texas also sets a form for each type, in Property Code sections 53.281 and 53.284. Its four forms have the same names as California's but different wording. A Texas waiver releases the owner, the owner's property, the contractor and the payment bond surety. In both states, a waiver that doesn't substantially follow the form in the law can't be enforced.

So check the form as well as the amounts. A waiver for a California job should be on the California form. If your subcontract also asks for waivers from the subcontractor's own suppliers and sub-subcontractors, check that each one is in the package.

The subcontractor's certificate of insurance and W-9#

Subcontracts usually set minimum insurance. They name the coverage types, the limits and who must be an additional insured. The subcontractor shows its coverage with a certificate of insurance, usually an ACORD 25. Here's one from an HVAC contractor.

Parties
FieldExtracted valueConfidence
Issue date2026-09-18
ACORD version2016/03
ProducerAllegheny Risk Partners LLC
InsuredKeystone HVAC LLC
Insurer A · NAICBrightwater Casualty Company · 21873
Insurer B · NAICBrightwater Specialty Insurance Co. · 34418
Insurer C · NAICLaurel Highlands Mutual Insurance Co. · 13052
Keystone HVAC LLC's certificate. General liability shows $1,000,000 each occurrence and auto shows a $1,000,000 combined single limit. Both run 07/01/2026 to 07/01/2027, with additional insured and waiver of subrogation marked.

Check each line against the subcontract. The limits should meet the minimums, and the policies should cover the months left on the job. On this certificate, workers' compensation ends on 03/15/2027, months before the other policies. If the job runs past that date, you'll need the renewed certificate. Check the certificate holder and the additional insured boxes against what the subcontract asks for.

The ACORD 25 says it's issued as a matter of information only and confers no rights on the certificate holder. It also says that if the holder is an additional insured, the policy must have additional insured provisions or be endorsed. An endorsement here is a written change to the policy. So ask for the additional insured endorsement and keep it with the certificate. ACORD 25 data extraction lists every field and check.

Docsumo reads ACORD forms, and it emails vendors for a missing or updated certificate. Checking a certificate against contract requirements is a cross-document check, on the Enterprise plan. Vertikal RMS, a risk management company, used Docsumo for COI verification by capturing ACORD forms. The certificate of insurance tracking page shows the checks.

The W-9 before the first payment

Ask each new subcontractor for a W-9 when you set it up as a vendor. The form gives you the subcontractor's correct taxpayer identification number (TIN). You need that number for the information returns you file with the IRS. Check that the name on the W-9 matches the subcontract and your vendor record. W-9 data extraction covers the fields and checks.

How automation fits the way you pay subcontractors#

Packages come in by email, by upload or through the API. Docsumo has an inbox for emails, so a shared AP mailbox can pass attachments straight to it. When a package arrives as one PDF, Docsumo's AI Split divides it into separate documents. AI Split takes a plain-English definition of each document type, which you give it. Splitting and auto-classification are on the Business plan.

  • Email inbox
  • Uploads
  • API
API and webhooks
  1. 01Split the package
  2. 02Read each document
  3. 03Check against the subcontract
  4. 04Route invoices for approval
Your accounting system
One subcontractor's monthly package, from the inbox to your accounting system

Docsumo isn't limited to invoices. Large language models (LLMs) turn the text it reads into fields, so it can read any document an LLM can read. That includes a pay application, a lien waiver or your own form. A field the software isn't sure of goes to a person. You decide how sure is sure enough by setting a confidence threshold for each field. Clicking a field highlights the line in the document it came from.

Checks that need one document, such as the math on the G702, are steps you add to the workflow. A step can call an LLM or run your own Python code. Checks between documents are on the Enterprise plan. One compares a pay application with the approved schedule of values. Matching a supplier invoice to its PO and receipt is another, and the accounts payable automation page walks through that match. Docsumo also flags an invoice that duplicates one already received.

Invoices then go to approvers by the rules you set, on the Business plan. A rule can use any field, such as the job or the amount. Approvers get an email, an invoice not approved in the time you set is escalated, and the audit log records each decision. Docsumo doesn't pay subcontractors, and it doesn't create POs. Checked data goes to your accounting system through the API and webhooks, and Docsumo is cloud only.

Our take. Pay applications differ from one general contractor to the next. Some use AIA forms and some use their own. Retainage rates, insurance minimums and approval steps change with each subcontract. Set the software up around the forms you receive, the checks your subcontracts call for and the approval steps you already use. Don't change how you pay subcontractors to suit a tool.

Try it on last month's pay applications#

Bring the packages that three or four subcontractors sent last month to a demo, exactly as they arrived. Include one with a change order, and one from a job in another state, with its lien waiver on that state's form. Then check two things. Did the software flag a G702 line that didn't add up from the others? That check is a step you add to the workflow. Did it match each waiver to the right payment? That's a cross-document check, on the Enterprise plan. If it did both on your own files, your team can review what it flags instead of doing those checks by hand.

Book a demo with a month of your subcontractor pay applications, or start a free trial.

Frequently asked questions#

What is construction AP automation?

Construction AP automation is software for a general contractor's accounts payable team. It reads what subcontractors and suppliers send, from invoices to pay applications, lien waivers and certificates of insurance. It checks each document, sends the ones that pass to approval and shows your team the rest with the reason.

What's the difference between an invoice and a pay application?

An invoice bills for goods or a job at an agreed price. A pay application bills for progress on a contract. It shows the contract sum and the approved change orders. It also shows the work completed and stored to date, the retainage and the earlier payments. AIA's G702 and G703 forms show all of these.

What is retainage in accounts payable?

Retainage is the part of each progress payment that the general contractor holds back, at the rate the subcontract sets. It's paid later, usually with the final payment. On AIA's G702, line 5 shows retainage on completed work and on stored materials.

What's the difference between a conditional and an unconditional lien waiver?

A conditional waiver takes effect only when the subcontractor receives the payment, so it can be signed before you pay. An unconditional waiver says the payment has been received. In California, a conditional waiver also needs evidence of payment. One example is the subcontractor's endorsement, its signature on the back of a check that has cleared.

What is the best accounts payable software for construction?

It depends on what your accounting system already does. If it already pays subcontractors and tracks retainage, you may only need software that reads and checks the documents. Docsumo does that part and sends the data on through the API and webhooks. If you also want payments in the same product, look at AP suites.

How much does it cost to process an invoice?

Ardent Partners' State of ePayables 2025, a sponsored analyst report, puts the average at $9.84 per invoice. It also finds that 18.4% of invoices become exceptions. The report counts only invoices. A pay application needs more checks, because you check it against the schedule of values, the subcontract and last month's application.